Envirotreat was commissioned by Seconique to assist with the management and appropriate disposal of three waaste soil stockpiles. The waste was the result of ongoing enabling works to facilitate the “letting” of the site to third parties.
Envirotreat previously undertook a comprehensive remediation programme prior to Seconique taking occupation in 2018. Third party enabling works, carried out subsequently, had resulted in the generation of three stockpiles onsite. To facilitate the letting of the land the stockpiles required assessment, sampling / analysis / classification and appropriate disposal.
Envirotreat sampled the stockpiles in accordance with the prepared sampling plan. The resulting analysis was assessed in accordancae with WM3 and suitably licenced facilities sourced in order to ensure compliant disposla of the waste soil.
The works were completed within two weeks with all soils transported and disposed of in a fully legal and compliant manner. Both real-time dust and reassurance air monitoring were carried out throughout the duration works.