Hydrocarbon Remediation Ford Bridgend

Site investigation undertaken by Arcadis, indicated the requirement for hydrocarbon remediation following an historical heating oil spill near the boiler house.

Envirotreat were invited by Arcadis to provide remediation and disposal costs for hydrocarbon impacted soils.

Envirotreat initiated attended the Ford site June 2020 to undertake the tendered works, returning in November 2020 to complete the remediation works.

The Ford Engine Plant at Bridgend closed following the cessation of production in September 2020.

Delivering land you can develop

Envirotreat are a specialist remediation solution provider and sole providers of E-Clay technology