Thomas Vale engaged Envirotreat to undertake the required remediation measures to address & enable discharge of the relevant planning application conditions relating to a new build on the campus.
Envirotreat undertook a series of shallow trial pits across the site to gain a better understanding of the contamination concerns associated with the made ground.
From which Envirotreat produced a Remediation Strategy / Method Statement which addressed the concerns with asbestos and other unexpected contamination issues. The factual report supported the required off-site disposal of soils.
Following completion of the development Envirotreat produced a comprehensive Verification Report, relating to site investigations undertaken, ‘watching brief at key stages (asbestos monitoring and capping layer) to enable the discharge of the respective planning conditions relating to the development.