Integrated remediation of former petrol filling station (Sandon).

Site Background & History

Integrated remediation of former petrol filling station.

Historically the Sandon site was a petrol filling station. The site being relatively small, 0.1 hectares. The  petrol station was closed in 2006 and above ground structures demolished.

The developer had planning permission to develop the site for the construction of three residential units.

During 2003 there was a petrol overfilling incident which resulted in a significant release of petrol into the underlying soils and groundwater. This was subject to extensive site investigations by Arcadis.

The underground storage tanks were removed in 2006. A Remediation Implementation Plan was developed by Arcadis in 2007 to address the identified soil and groundwater contamination. The  Remediation Implementation Plan proposed the excavation of impacted soils in combination with the use of Vacuum Enhanced Recovery and addition of an Oxygen Release Agent to address the residual groundwater contamination.

Hydrocarbon impacted soils were removed in 2009 under the supervision of Arcadis.

In 2010 Arcadis concluded that a groundwater contamination plume (including free product) remained, migrating off the site in a northerly direction.

The proposed Vacuum Enhanced Recovery and addition of an Oxygen Release Agent to address the residual groundwater contamination was the envisaged to take 24 months. This approach did not fit with any development proposals for the site, due to funding.

In 2012 the developer invited Envirotreat to submit revised remediation proposals (prior to their purchasing of the site), to assess the commercial viability of the scheme. The developer required the confidence that the site could be effectively remediated and that planning conditions could be discharged prior to purchase.

Remediation Strategy

The Envirotreat remediation strategy combined source and pathway treatment to provide an integrated treatment approach and essentially comprised of the following:

  • Free product removal
  • Treatment of source contamination (soils and associated groundwater) by E-Clay Stabilisation
  • Installation of an E-Clay Permeable Reactive Barrier to remediate contaminated groundwater (pathway treatment)

Remediation Strategy

The first phase of the remediation works involved the ex-situ treatment of the contaminated soils utilising E-Clay Stabilisation.

An E-Clay permeable reactive barrier was installed along the majority of the northern site boundary to intercept and treat the natural flow of potentially contaminated groundwater migrating from the site.

Validation

Representative samples of treated soils were leach tested and compared with the derived leachate target criteria for Total Petroleum
Hydrocarbons, BTEX and Polycyclic Aromatic Hydrocarbons. All leachate values were compliant with the agreed remediation target criteria

Existing boreholes located immediately downstream of the barrier installation in the adjoining footpath was used to monitor groundwater quality post remediation. The results demonstrated satisfactory compliance with the designated remediation target criteria.

In addition, Envirotreat undertook gas monitoring, gas membrane and capping validation.

Delivering land you can develop

Envirotreat are a specialist remediation solution provider and sole providers of E-Clay technology